We finally made it back to the boat project on July 5th, 2010 with a whole raft of things to do.
In the winter of 2009 they had a lot of snow here and the huge snow load took a real toll on the railings.
See 2009 Damage for the damage.
After analyzing the damage, I decided to completely enclose the ship and make her weather tight so I no longer have a need for a tarp.
It is going to be outside it's whole life so we may as well start now.
So now that I have decided to leave her open year round I need to do the following outside work.
As we progress through the summer I will put green checkmarks next to the completed items.

Scrub a dub dub !!!
Step 1: Finish the framing around the front windshield.
Step 2: Redo the current hatch opening for the rear companionway.
Step 3: Build a hatch cover for the rear companionway.
Step 4: Build companionway Doors.
Step 5: Get the rudder and steering gear installed and functioning.
  1. Install and Balance Rudder
  2. Install Helm Hydraulic Cylinder
  3. Install Pilot House Steering Pump 
  4. Install Outside Steering Station (Helm and captain's seat)
  5. Plumb and test
Step 6: Repair the rotten deck.
Step 7: Repair the railing on the aft deck.
Step 8: Repair the aft deck.
Step 9: Convert anchor windlass from hydraulic to electric.
Step 10: Sand and refinish all the wood that has been affected by the weather.
Step 11: Remove old scaffolding around the rear of the boat.